Major progress made in ShenJiang Railway construction
2024-12-19

The ShenJiang Railway (Shenzhen-Jiangmen Railway) construction has seen major progress recently, as the upper crossbeam of Main Tower #158 of the Jiya Waterway Grand Bridge has completed pouring, 12 days ahead of schedule.


1219-2.png


Spanning 6,896.2 meters, Jiya Waterway Grand Bridge is designed with a steel-concrete composite girder cable-stayed main bridge. The newly poured upper crossbeam is placed at a height of 91.4 meters.